822 Gaines Costs   September 2, 2008
       
Project Original Estimates 2007 Estimates Actual   
1 - Reframing   Mark Construction   $20,000 $23,000 $22,768  
Roofing-Mark Construction  $11,000 $11,000 $11,000  
       Soffits  Mark Construction   $3,000 $2,924  
       Interior framing     $3,000 $3,301  
2 - Siding\Trim   $3,000 $5,772  
Gutters   $600 $1,815  
3 - Windows   $5,000 $5,500 $8,101  
4- Painting  $5,000 $5,000 $3,408  
5 - Mechanicals        
     Heating \Air    $10,000 $7,800 $7,500  
     Insulation  $2,600 $2,600 $1,493  
  Plumbing   $6,700 $6,700 $9,048  
  Electrical   $5,000 $5,000 $4,650  
6 - Interior        
      Drywall $7,000 $7,000 $7,601  
Flooring $5,000 $5,000 $5,061  
Interior Finish work   $2,000 $3,288  
7 - Staircase   $3,000 $3,018  
8 - Porch \bay roof \shed   $2,500 $4,868  
Basement door and windows   $1,000 $539  
9 - Garage Repair $3,000 $6,000 $6,521  
10 - Hauling   $800 $1,344  
11 - Miscellaneous costs     $1,817  
Tim-Bor pressure spray    $312 $312  
Taxes   $235 $412  
12 - Utilities\hookup   $1,000 $2,271  
13 - Appliances\Cabinets\Fixtures $5,000 $5,000    
                Appliances     $212  
                Cabinets     $1,491  
                Fixtures     $3,176  
14 - Interest QCHC Loan   $2,400 $3,580  
15 - ARS Hardware, trim, doors, etc  $4,000 $4,000 $6,725  
Landscaping   $1,000    
General Contractor GRG $8,000 $8,000    
Selling Costs  $2,100 $2,400    
Legal Fees $1,000 $1,000 $760  
Insurance   $600 $1,228  
         
Totals  $100,400 $129,447 $136,003  

 

Volunteer service as of August10,2008   3,016 hours